Triad provided surveying and construction layout services for Herbruck’s Project Freebird, overseen by a Professional Land Surveyor licensed in the Commonwealth of Pennsylvania. The scope of services included the following tasks, based on project plans and prior experience.
Survey Control: Triad’s surveying personnel recovered and verified existing horizontal and vertical survey control. New survey control was established as necessary to provide stakeout for the project. This task included the establishment of a minimum of four (4) bench marks on-site and the preparation of a sketch.
Process Building Control: Triad provided computations and stakeout services for the Process Building. This included staking six (6) control/grid lines in a North/South direction and six (6) control/grid lines in an East/West direction. The task also involved the stakeout of each building corner with offsets. A grade sheet and sketch were prepared. A maximum of one (1) mobilization was required to complete the tasks in this scope.
Barn Building Control: Triad provided computations and stakeout services for Barn Buildings C through F and the Manure Building. This included staking seven (7) control/grid lines in a North/South direction and three (3) control/grid lines in an East/West direction. The stakeout of each building corner with offsets was also included, along with grade sheet and sketch preparation. A maximum of three (3) mobilizations were required to complete this task.
These surveying services were completed efficiently, supplying accurate layout for the construction of the various buildings within the project.